HB1438 (2008) Detail

Relative to a capital appropriation for the construction of the Hampton-Exeter district courthouse.


HB 1438 – AS INTRODUCED

2008 SESSION

08-2175

10/03

HOUSE BILL 1438

AN ACT relative to a capital appropriation for the construction of the Hampton-Exeter district courthouse.

SPONSORS: Rep. Stiles, Rock 15; Rep. Flockhart, Rock 13; Rep. Weare, Rock 14; Rep. Nowe, Rock 9; Rep. J. Day, Rock 13; Sen. Estabrook, Dist 21; Sen. Hassan, Dist 23; Sen. Fuller Clark, Dist 24; Sen. Barnes, Dist 17

COMMITTEE: Public Works and Highways

ANALYSIS

This bill provides for a capital appropriation for the construction of the Hampton-Exeter district courthouse if the Merrimack district courthouse construction is not begun.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Explanation: Matter added to current law appears in bold italics.

Matter removed from current law appears [in brackets and struckthrough.]

Matter which is either (a) all new or (b) repealed and reenacted appears in regular type.

08-2175

10/03

STATE OF NEW HAMPSHIRE

In the Year of Our Lord Two Thousand Eight

AN ACT relative to a capital appropriation for the construction of the Hampton-Exeter district courthouse.

Be it Enacted by the Senate and House of Representatives in General Court convened:

1 Capital Budget; Hampton-Exeter District Court. Amend 2007, 264:1, II, 3 and the following footnote to read as follows:

3. Merrimack District Courthouse; Hampton-Exeter

District Courthouse * 7,000,000

* The sum appropriated in subparagraph A. 3 shall first be for the Merrimack district courthouse and shall not be spent, obligated, or encumbered until land suitable for a standard court facility similar to the Dover district court layout has been acquired prior to July 1, 2008 provided that there is no cost of land acquisition by the state and that site work and infrastructure costs can be accomplished within the sum appropriated or the authority shall lapse. Upon such lapse of authority, the sum appropriated shall be for the construction of the Hampton-Exeter district courthouse.

2 Effective Date. This act shall take effect upon its passage.