HB 25-FN-A – AS AMENDED BY THE HOUSE

3Apr2013… 1150h

2013 SESSION

13-1020

10/09

HOUSE BILL 25-FN-A

AN ACT making appropriations for capital improvements.

SPONSORS: Rep. Campbell, Hills 33

COMMITTEE: Public Works and Highways

ANALYSIS

This bill makes appropriations for capital improvements for the biennium and extends certain lapse dates for previous appropriations.

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

Explanation: Matter added to current law appears in bold italics.

Matter removed from current law appears [in brackets and struckthrough.]

Matter which is either (a) all new or (b) repealed and reenacted appears in regular type.

3Apr2013… 1150h

13-1020

10/09

STATE OF NEW HAMPSHIRE

In the Year of Our Lord Two Thousand Thirteen

AN ACT making appropriations for capital improvements.

Be it Enacted by the Senate and House of Representatives in General Court convened:

1 Capital Appropriations. The sums hereinafter detailed are hereby appropriated for the projects specified to the departments, agencies, and branches named:

I. Adjutant General

A. Unspecified Minor Military Construction $5,500,000

Less Federal -5,500,000

Net state appropriation subparagraph A 0

B. Land For Manchester Field Maintenance Shop 1,000,000

C. Statewide Readiness Center Restoration and Modernization 1,750,000

Less Federal -875,000

Net state appropriation subparagraph C 875,000

D. Federal Property Conv to Readiness Cntr and Maint. Shop 1,000,000

Less Federal -750,000

Net state appropriation subparagraph D 250,000

E. Manchester Field Maintenance Shop Design 2,500,000

Less Federal -2,500,000

Net state appropriation subparagraph E 0

F. Columbarium Expansion 675,000

Less Federal -675,000

Net state appropriation subparagraph F 0

Total state appropriation paragraph I $2,125,000

II. Department of Administrative Services

A. Statewide Projects

1. Emergency Repairs-All State Owned Facilities $500,000

2. Statewide Energy Efficiency Improvements 500,000

B. General Services

1. Records and Archives-New Roof 480,000

2. DHHS HVAC Repairs 775,000

3. Morton Building Cooling Tower 217,000

4. State House Dome Repair 472,445

5. Health and Human Services Vault Upgrade 145,000

6. House of Representatives Voting System Software-

LED Summary Displays 560,000

7. State House Annex – Replace Roof 450,000

8. Facilities Condition Analysis 400,000

9. Legislative Office Building Elevator Upgrade 330,000

C. Facilities and Asset Management

1. Dolloff Domestic Water Main Replacement 260,000

2. Driveway/Parking and Walkway Paving Phase 3 790,000

3. Main Building Asbestos Abatement/Lead Paint Control 630,000

4. Main Building Window Replacement Phase 1 450,000

D. Court Facilities

1. Coos County Courthouse-Bullnose Repairs 240,000

2. Concord District Courthouse-New Roof 245,000

3. Rockingham County Superior Court – Replace Roof 551,250

4. Rockingham County Superior Court – Replace Cooling Tower 217,000

5. Lebanon District Court – Replace Roof 142,000

Total state appropriation paragraph II $8,354,695

III. Department of Agriculture, Markets and Food

A. New Hampshire Building-Eastern States Expo-Roof Replacement $235,000

Total state appropriation paragraph III $235,000

IV. Department of Corrections

A. 224 Bed Women's Prison and Transitional Housing Facility* $38,000,000

B. Remove and Replace 2, 20,000 Gallon Oil Tanks and

one 5,000 Gallon Diesel Tank 130,000

C. Electronic Medical Records System 500,000

Total state appropriation paragraph IV $38,630,000

* The project in subparagraph A shall utilize the construction management method of contracting. The design for the project shall be submitted no later than April 1, 2014 to the capital budget overview committee for approval and shall include sufficient acreage for possible expansion to 350 beds for future needs. The primary location for the siting of the facility shall be in Concord on state lands adjacent to the men’s prison. If an alternative location is deemed necessary, the siting for the facility shall be subject to prior approval of the capital budget overview committee. The department shall report quarterly to the capital budget overview committee on the status of the project.

V. Department of Education

A. Renovation of CTE Center-Whitefield- State Share* $13,500,000

B. Renovation of CTE Center-Salem- State Share * 10,775,000

Total state appropriation paragraph V $24,275,000

* The funds appropriated to the department of education in subparagraphs A and B for CTE centers in Whitefield and Salem shall not be spent, obligated, or encumbered until such time as an action plan has received approval from the capital budget overview committee.

VI. Department of Environmental Services

A. Dam Repairs and Reconstruction $ 3,115,000

B. Drinking Water SRF Matching Funds 3,487,988

C. Clean Water SRF Matching Funds 1,970,352

Less Other Funds * -1,970,352

Net state appropriation subparagraph C 0

D. Flood Warning and Operations Improvements 225,000

Total state appropriation paragraph VI $6,827,988

* To provide funds for the appropriation made in subparagraphs VI, C, the state treasurer is hereby authorized to borrow upon the credit of the state not exceeding the sum of $1,970,352 and for said purpose may issue bonds and notes in the name of and on behalf of the state of New Hampshire in accordance with RSA 6-A. Payments of principal and interest on the bonds and notes pursuant to subparagraph VI, C shall be made from the state water pollution control and drinking water revolving loan funds established in RSA 486:14.

VII. Department of Health and Human Services

A. Glencliff Fire and ADA Code Compliance 470,000

B. APS Security and Safety Upgrades 500,000

C. Glencliff Residential Building Security 225,000

D. Glencliff Hydro Dam Repair 655,000

E. New Heights Incremental Modernization 16,843,842

Less Federal -11,959,128

Net state appropriation subparagraph E 4,884,714

F. Child Support Systems Maintenance and Enhancement 5,550,000

Less Federal -3,663,000

Net state appropriation subparagraph F 1,887,000

G. Food Protection Data System 280,000

Less Other Funds * -210,000

Net state appropriation subparagraph G 70,000

H. Psychiatric Crisis Beds 2,150,000

I. Bridges Modernization Project 1,000,000

Less Federal -500,000

Net state appropriation subparagraph I 500,000

Total state appropriation paragraph VII $11,341,714

* To provide funds for the appropriation made in subparagraph VII, G, the state treasurer is hereby authorized to borrow upon the credit of the state not exceeding the sum of $210,000 and for said purpose may issue bonds and notes in the name of and on behalf of the state of New Hampshire in accordance with RSA 6-A. Payments of principal and interest on the bonds and notes pursuant to subparagraph VII, G shall be made from the public health services special fund under RSA 143:11.

VIII. Department of Information Technology

A. Business One Stop $2,000,000

B. Enterprise Licensing Solution 2,295,000

C. Network Access Control 560,000

Total state appropriation paragraph VIII $4,855,000

IX. Judicial Branch

A. E-Court Initiative $3,500,000

B. Furnishings and Security Equipment-Cheshire

County Courthouse 200,000

Total state appropriation paragraph IX $3,700,000

X. Department of Justice

A. Installation of Video Conferencing Hardware $62,000

B. ProLaw Upgrade 497,010

Less Other Funds * -27,187

Net state appropriation subparagraph B 469,823

Total state appropriation paragraph X $531,823

* To provide funds for the appropriation made in subparagraphs X, B, the state treasurer is hereby authorized to borrow upon the credit of the state not exceeding the sum of $27,187 and for said purpose may issue bonds and notes in the name of and on behalf of the state of New Hampshire in accordance with RSA 6-A. Payments of principal and interest on the bonds and notes pursuant to subparagraph X, B shall be made from agency income.

XI. Liquor Commission

A. New Salem Retail Store $5,400,000

Less Other Funds * -5,400,000

Net state appropriation subparagraph A 0

B. Hampton North and South Renovations 6,380,000

Less Other Funds * -6,380,000

Net state appropriation subparagraph B 0

C. New Epping Retail Store 3,850,000

Less Other Funds * -3,850,000

Net state appropriation subparagraph C 0

D. New Warner Retail Store 3,500,000

Less Other Funds * -3,500,000

Net state appropriation subparagraph D 0

E. Renovate Space from Retail to Office 780,000

Less Other Funds * -780,000

Net state appropriation subparagraph E 0

F. Nashua Retail Store – Parking Lot 80,000

Less Other Funds* -80,000

Net state appropriation subparagraph F 0

Total state appropriation paragraph XI $0

* To provide funds for the appropriations made in paragraph XI, the state treasurer is hereby authorized to borrow upon the credit of the state not exceeding the sum of $19,990,000 and for said purpose may issue bonds and notes in the name of and on behalf of the state of New Hampshire in accordance with RSA 6-A. Payments of principal and interest on the bonds and notes shall be made from the liquor commission fund established in RSA 176:16.

XII. Department of Resources and Economic Development

A. State Parks Improvements $1,200,000 B. Roofing and Repair-State Parks 1,255,000

C. Sherman Adams Building Entrance Replacement 375,000

D. Hampton North Beach Seawall Repair 1,000,000

Less Other Funds* -1,000,000

Net state appropriation subparagraph D 0

E. Radio Systems 233,000

F. Fire Tower Repairs 360,000

G. Memorial, 400th Anniversary- Rye Harbor State Park** 40,000

Total state appropriation paragraph XII $3,463,000

* To provide funds for the appropriations made in subparagraph D, the state treasurer is hereby authorized to borrow upon the credit of the state not exceeding the sum of $1,000,000 and for said purpose may issue bonds and notes in the name of and on behalf of the state of New Hampshire in accordance with RSA 6-A. Payments of principal and interest on the bonds and notes shall be made from the special fund and the Hampton Beach capital improvements fund under RSA 216:3.

** The state appropriation in subparagraph G shall be a state match against private funds raised, up to $40,000, for the purpose of constructing the memorial commemorating the 400th anniversary of the discovery of the Isles of Shoals by John Smith at Ragged Neck in Rye Harbor State Park.

XIII. Department of Safety

A. Radio Interoperability Infrastructure

Upgrade – General Fund Portion $300,000

Total state appropriation paragraph XIII $300,000

XIV. Secretary of State

A. Shelving Replacement and Fire Suppression $675,000

Total state appropriation paragraph XIV $675,000

XV. Department of Transportation

A. Aeronautics, Rail and Transit

1. 5 percent Match for Federal Aviation Admin Projects $24,972,073

Less Federal -23,307,397

Net state appropriation subparagraph 1 1,664,676

2. Public Transit Bus and Facility Matching Funds 545,000

3. Freight Rail – State Matching Funds 600,000

Total state appropriation paragraph XV $2,809,676

XVI. Veterans Home

A. Equipment Upgrades $1,650,000

Less Federal -1,072,500

Net state appropriation subparagraph A 577,500

Total state appropriation paragraph XVI $577,500

XVII. Community College System of New Hampshire

A. Lump Sum for Capital Projects $13,000,000

Less Other Funds * -5,000,000

Net state appropriation subparagraph A 8,000,000

Totals for paragraph XVII $8,000,000

Total state appropriation section 1 $116,701,396

* To provide funds for the appropriations made in subparagraph XVII, A the state treasurer is hereby authorized to borrow upon the credit of the state not exceeding the sum of $5,000,000 and for said purpose may issue bonds and notes in the name of and on behalf of the state of New Hampshire in accordance with RSA 6-A. Payments of principal and interest on the bonds and notes shall be made from student fees.

2 Capital Appropriation; Highway Funds. The sums hereinafter detailed are appropriated for the projects specified:

I. Department of Safety

A. Radio Interoperability Infrastructure

Upgrade – Highway Fund Portion $1,700,000

B. Fire Academy Bldg Upgrades and Critical Maintenance 375,000

Less Other Funds * -375,000

Net state appropriation subparagraph B 0

C. Land Acquisition and Improvement 1,000,000

Less Other Funds** -1,000,000

Net state appropriation subparagraph D 0

D. NH Marine Patrol Headquarters 9,379,313

Less Other Funds ** -9,379,313

Net state appropriation subparagraph D 0

Total state appropriation paragraph I $1,700,000

* To provide funds for the appropriation made in subparagraph I, B, the state treasurer is hereby authorized to borrow upon the credit of the state not exceeding the sum of $375,000 and for said purpose may issue bonds and notes in the name of and on behalf of the state of New Hampshire in accordance with RSA 6-A. Payments of principal and interest on the bonds and notes pursuant to subparagraph I, B shall be made from the fire standards and training and emergency medical services fund established in RSA 21-P:12-d.

** To provide funds for the appropriations made in subparagraphs I, C and D, the state treasurer is hereby authorized to borrow upon the credit of the state not exceeding the sum of $10,379,313 and for said purpose may issue bonds and notes in the name of and on behalf of the state of New Hampshire in accordance with RSA 6-A. Payments of principal and interest on the bonds and notes pursuant to subparagraphs I, C and D shall be made from the navigation safety fund established under RSA 270-E:6-a.

II. Department of Transportation

A. Underground Fuel Tank Replacement-Statewide $3,500,000

B. Project Development Computer Systems Replacement 3,260,000

C. JOMB Data Center HVAC and UPS Replacement 510,000

D. Welcome Information Center Critical and Deferred Maintenance 967,500

E. New Patrol Shed PS528 Derry, Design, Engineering, and Construction 3,180,000

F. New Patrol Shed PS602 Strafford, Design 160,000

Total state appropriation paragraph II $11,577,500

Total state appropriation section 2 $13,277,500

3 Capital Appropriation; University System of New Hampshire. The sums hereinafter detailed are appropriated for the projects specified:

A. Lump Sum for Capital Projects $7,500,000

Total state appropriation section 3 $7,500,000

4 Expenditures; General. The appropriation made for the purposes mentioned in sections 1 and 2 of this act and the sums available for those projects shall be expended by the trustees, commissions, commissioner, or department head of the institutions and departments referred to herein; provided that all contracts and projects and plans and specifications therefor shall be awarded in accordance with the provisions of RSA 21-I and RSA 228.

5 Expenditures; University System of New Hampshire.

I. The appropriations made for the purposes mentioned in section 3 of this act and the sums available for these projects shall be expended by the trustees of the university system of New Hampshire. All contracts for the construction of all or any part of said buildings or facilities shall be let only after competitive sealed bids have been received and only after an advertisement calling for such bids has been published at least once in each 2 successive calendar weeks in a newspaper of general circulation in New Hampshire or in a trade journal known to be circulated among the contractors from whom bids will be sought with the state of New Hampshire or elsewhere in the area. The first publication of such advertisement shall be not less than 30 days prior to the date the bids will be received. All conditions considered, wherever possible, it is recommended that the services of New Hampshire architectural and construction firms be considered within the discretion of the trustees.

II. The appropriations made in section 3 of this act are available for all costs incidental to the completion of the projects enumerated including the costs of the services of architects, engineers, and other consultants of such kind and capacity as the university system board of trustees, in its discretion, may wish to employ on such terms and conditions as the board determines. These moneys shall be spent under the direction of the university system board of trustees.

III. If, in the judgment of the trustees of the university system, just cause exists indicating the lowest bid should be rejected, then the contract may be awarded to the next lowest bidder; or, if the next lowest bid should be rejected, the contract may be awarded to the third lowest bidder.

IV. The board of trustees of the university system has the right to reject any and all bids and, if the lowest bid is in excess of the appropriation, the board has the right to negotiate with the low bidder or with the 3 lowest bidders for a contract for the construction upon terms considered most advantageous to the university. If only one bid is received, the board of trustees may negotiate a contract for the construction on terms considered most advantageous to the university system and to the state. Any authorization contained in this act which is at variance with the requirements of applicable federal law and regulations shall be controlled by the terms of the federal law and regulations.

V. Notwithstanding paragraphs I, III, and IV, the sums appropriated by section 3 of this act for all or any of the projects listed in section 3 of this act, may be expended and awarded by the trustees of the university system; provided that all contracts for all or any part of the building or facilities shall follow construction management procurement procedures and guidelines. If the trustees select construction management pursuant to this paragraph, paragraphs I, III, and IV shall not apply and the trustees shall retain the right to reject or negotiate following accepted construction management practices.

6 Land Acquisition. Any land acquired under the appropriations made in sections 1 and 2 of this act, if any, as may be acquired under the appropriation except such land if any as may be acquired for the water resources board, shall be purchased by the commissioner of the department of transportation or the commissioner of administrative services, as appropriate, with the approval of governor and council.

7 Bond Authorized. To provide funds for the total of the appropriations of state funds made in sections 1, 2, and 3 of this act, the state treasurer is hereby authorized to borrow upon the credit of the state not exceeding the sum of $176,430,748 and for said purposes may issue bonds and notes in the names and on behalf of the state of New Hampshire in accordance with the provisions of RSA 6-A. The source of funds shall be as follows: general fund $124,201,396, highway funds $13,277,500, and other funds $38,951,852.

8 Payments.

I. The payment of principal and interest on bonds and notes issued for the projects in sections 1 and 3 shall be made when due from the general funds in the state.

II. The payment of principal and interest on bonds issued for the projects in section 2 shall be made from the highway fund.

9 Powers of Governor and Council. The governor and council are hereby authorized and empowered:

I. To cooperate with and enter into such agreements with the federal government, or any agency thereof, as they may deem advisable, to secure federal funds for the purposes hereof.

II. To accept any federal funds which are, or become available for any project under sections 1 and 2 of this act beyond the estimated amounts. The net appropriation of state funds for any project for which such additional federal funds are accepted shall be reduced by the amount of such additional funds, and the amount of bonding authorized by section 7 of this act shall be reduced by the same amount.

10 Transfers. The individual project appropriations provided in sections 1 and 2 of this act shall not be transferred or expended for any other purposes; provided that if there is a balance remaining after an individual project, which is fully funded by state funds, is completed, accepted, and final payment made, said balance or any part thereof may be transferred by Governor and Council, to any other individual project or projects, which are also fully funded by state funds, within the same section and from the same funding source, provided that prior approval of the capital budget overview committee is obtained.

11 Reduction of Appropriation and Bonding Authority. If the net appropriation of state funds for any project provided for by sections 1 and 2 of this act is determined on the basis of an estimate of anticipated federal, local, or other funds, and if the amount of such funds actually received or available is less than said estimate, then the total authorized cost for such projects and the net appropriation of state funds thereof shall be reduced by the same proportion as the proportion by which federal, local, or other funds are reduced. The amount of bonding authorized by section 7 of this act shall be reduced by the amount that the appropriation of state funds is reduced pursuant to this section.

12 Bureau of Public Works Design and Construction Inspection Services; Davis-Bacon Act Compliance. The appropriations for those projects which are managed by the bureau of public works design and construction, department of administrative services, may be expended to fund temporary personnel for the purpose of providing construction inspection services and Davis-Bacon Act Compliance services for projects utilizing federal funds, for those projects included in this act.

13 Project Purpose Amended; Adjutant General; 2009 Capital Budget. Amend 2009, 145:1, I, B to read as follows:

B. D&E Storage Buildings- Additional Power & Lighting; Power and Lighting Improvements – Statewide 282,000

Less Federal -141,000

Net state appropriation subparagraph B 141,000

14 Project Purpose Amended; Administrative Services; 2009 Capital Budget. Amend 2009, 145:1, II, C, 3 to read as follows:

3. Main Building Kitchen, Bakery [Roof Repair], Connector, and Industrial

Shop - Raze Buildings and Create Parking Lot 210,000

15 Project Purpose Amended; Administrative Services; 2011 Capital Budget. Amend 2011, 253:1, II, B, 4 to read as follows:

4. Main Building Kitchen [Roof Repair], Bakery, Connector, and Industrial

Shop - Raze Buildings and Create Parking Lot 500,000

16 Project Purpose Amended, Department of Safety, 2011 Capital Budget. Amend 2011, 253:2, II, A to read as follows:

A. Standby Generator Replacement Hayes Bldg (33 Hazen Dr.),

Computer Room A/C Upgrade, and DMV HQ Generator $775,000

17 Project Purpose Amended; Administrative Services; 2011 Capital Budget. Amend 2011, 253:1, II, B, 2 to read as follows:

2. Lakes Region Facility Campus Site Environmental

Survey II, and DOIT Productivity Suite Desktop Security * 300,000

18 Project Purpose Amended; Administrative Services; Former Corrections Project; 2009 Capital Budget. Amend 2009, 145:1, IV, F, as amended by 2011, 253:14, to read as follows:

F. Stormwater/Sewer System-EPA order #05-13, and

DOIT Productivity Suite Desktop Security 575,000

19 Project Purpose Amended; Administrative Services; 2009 Capital Budget. Amend 2009, 145:15, II(b) to read as follows:

(b) Northern Carroll County New Roof, and DOIT Productivity

Suite Desktop Security $130,000

20 Project Purpose Amended; Administrative Services; 2009 Capital Budget. Amend 2009, 145:1, II, B, 1 through 5 to read as follows:

1. Johnson Hall Renovations/Repairs, and DOIT Productivity

Suite Desktop Security 53,000

2. LOB Critical Maintenance, and DOIT Productivity

Suite Desktop Security 2,900,000

3. DHHS Replace Chillers, Tower Repairs 780,000

4. Johnson Hall New Roof, and DOIT Productivity

Suite Desktop Security 198,000

5. State Library-Repoint Brick, Internal Repairs, and

DOIT Productivity Suite Desktop Security 1,345,000

21 Project Purposes Amended; Administrative Services; 2009 Capital Budget. Amend 2009, 145:16, II, (a) through (d) to read as follows:

(a) Supreme Court Parking Lot, and DOIT Productivity

Suite Desktop Security 394,295

(b) Supreme Court ADA Access, and DOIT Productivity

Suite Desktop Security 275,000

(c) Morton Building New Roof 650,000

(d) State House Ice Stop System, and DOIT Productivity

Suite Desktop Security 80,000

22 Project Purpose Amended; Administrative Services; 2009 Capital Budget. Amend 2009, 145:1, II, C, 1 to read as follows:

1. Bow Brook Pond Dredging & Dam Stoplog, and

DOIT Productivity Suite Desktop Security 1,100,000

23 Project Purpose Amended; Department of Corrections; 2009 Capital Budget. Amend 2009, 145:1, IV, C to E to read as follows:

C. Residential Treatment Unit Phase 2, and DOIT Productivity

Suite Desktop Security 3,650,000

D. Admin East Wing-Upgrade Electric Wiring 79,000

E. MSU & Admin Bldg-Replace Sprinkler System, and

DOIT Productivity Suite Desktop Security 390,000

24 Unencumbered Balances Transferred; Department of Information Technology; Productivity Suite Desktop Security Project Authorized.

I. The sum of $3,000,000 from the unencumbered balances of the projects amended by sections 17 through 23 of this act are hereby transferred to the department of information technology for the purpose of funding the capital project of productivity suite desktop security.

II. All contracts and projects and plans and specifications therefor for the project authorized in this section shall be awarded in accordance with the provisions of RSA 21-I.

III. The appropriations in sections 17 through 23 of this act as amended and transferred in this section are hereby extended and shall not lapse until June 30, 2015.

25 Commission Established; Construction of 400th Anniversary Memorial at Ragged Neck in Rye Harbor State Park.

I. There is hereby established a commission to oversee the design, siting, and construction of a memorial commemorating the 400th anniversary of the discovery of the Isles of Shoals by John Smith at Ragged Neck in Rye Harbor State Park, using the funds appropriated in section 1, paragraph XII, G of this act.

II. The members of the commission shall be as follows:

(a) Two members of the house of representatives, one from each major political party, appointed by the speaker of the house of representatives.

(b) Two members of the senate, one from each major political party appointed by the president of the senate.

(c) The commissioner of the department of resources and economic development, or designee.

(d) The commissioner of the department of cultural resources, or designee.

(e) One person appointed by the governor.

III. Legislative members of the commission shall receive mileage at the legislative rate when attending to the duties of the commission.

IV. The commission shall advise the department of resources and economic development, division of parks and recreation, on the design, siting, and construction of a monument at Ragged Neck in Rye Harbor State Park commemorating the 400th anniversary of the discovery of the Isles of Shoals by John Smith. The commission shall approve the design and location of the memorial prior to construction. The commission shall also monitor the raising of private funds required for the state match to expend the state capital appropriation for the construction of the memorial.

V. The members of the commission shall elect a chairperson from among the members. The first meeting of the commission shall be called by the first-named house member. The first meeting of the commission shall be held within 45 days of the effective date of this section. Four members of the commission shall constitute a quorum. The commission shall meet as necessary until completion of the project.

26 Lapse Dates Extended to June 30, 2015. The following appropriations are hereby extended to June 30, 2015:

1. The appropriation made to the adjutant general in 2011, 253:1, I, A for statewide facilities improvements.

2. The appropriation made to the adjutant general in 2011, 253:1, I, B for readiness center restoration and modernization.

3. The appropriation made to the adjutant general in 2009, 145:1, I, B extended by 2011, 253:28, 2, and amended by section 13 of this act, for D and E storage buildings, additional power and lighting; power and lighting improvements – statewide.

4. The appropriation made to the adjutant general in 2007, 264:1, I, B extended by 2009, 145:19, 5 extended by 2011, 253:28, 9 for armory-statewide auxiliary power.

5. The appropriation made to the adjutant general in 2007, 264:1, I, F extended by 2009, 145:19, 9 extended by 2011, 253:28, 11 for regional training institute construction.

6. The appropriation made to the department of administrative services in 2011, 253:1, II, A, 1 for Rockingham county reseal/drainage.

7. The appropriation made to the department of administrative services in 2011, 253:1, II, B, 1 for Hugh Gallen OPS-FACP replacement.

8. The appropriation made to the department of administrative services in 2011, 253:1, II, B, 3 for driveway/parking and walkway paving phase 2.

9. The appropriation made to the department of administrative services 2011, 253:1, II, B, 4, as amended by section 15 of this act, for main building kitchen, bakery, connector, and industrial shop - raze buildings and create parking lot.

10. The appropriation made to the department of administrative services in 2011, 253:1, II, B, 5 for lakes region facility roof repair.

11. The appropriation made to the department of administrative services in 2011, 253:1, II, B, 6 for Hugh Gallen OPS main building ADA restrooms.

12. The appropriation made to the department of administrative services in 2011, 253:1, II, B, 7 for Philbrook Center renovation.

13. The appropriation made to the department of administrative services in 2011, 253:1, II, C, 1 for critical IT infrastructure.

14. The appropriation made to the department of administrative services in 2011, 253:1, II, C, 2 for ERP phase 2 HR and payroll systems.

15. The appropriation made to the department of administrative services in 2011, 253:1, II, D, 1 for emergency repairs-all facilities.

16. The appropriation made to the department of administrative services in 2011, 253:1, II, D, 2 for statewide energy efficiency improvements.

17. The appropriation made to the department of administrative services in 2011, 253:1, II, D, 5 for state house dome renovation and repair.

18. The appropriation made to the department of administrative services in 2011, 253:1, II, D, 6 for DHHS window repairs.

19. The appropriation made to the department of administrative services in 2011, 253:1, II, D, 7 for state house annex windows.

20. The appropriation made to the department of administrative services in 2011, 253:2, I, A for ERP phase II-highway funds.

21. The appropriation made to the department of administrative services in 2009, 145:1, II, A, 1 extended by 2011, 253: 28, 12 for Hillsborough county north asbestos abatement.

22. The appropriation made to the department of administrative services in 2009, 145:1, II, A, 2 extended by 2011, 253:28, 13 for master plan for the courts.

23. The appropriation made to the department of administrative services 2009, 145:1, II, C, 3, as extended by 2011, 253:28, 21, as amended by section 14 of this act, for main building bakery, kitchen, connector, and industrial shop - raze buildings and create parking lot.

24. The appropriation made to the department of administrative services in 2009, 145:1, II, C, 4 extended by 2011, 253:28, 22 for Hugh Gallen office park parking.

25. The appropriation made to the department of administrative services in 2009, 145:1, II, E, 1 extended by 2011, 253:28, 24 for state owned facilities energy and lighting improvements.

26. The appropriation made to the department of administrative services in 2009, 145:1, II, E, 3 extended by 2011, 253:28, 25 for ERP information technology phase II.

27. The appropriation made to the department of administrative services in 2005, 259:1, II, A, 2 amended by 2007, 264:14 extended by 2007, 264:29, IX extended by 2009, 145:19, 12 extended by 2011, 253:28, 30 for Cheshire and Merrimack county courthouse design, Keene district court design and renovate temporary space.

28. The appropriation made to the department of administrative services in 2003, 240:1, II, C, 2 extended by 2005, 259:25, XVI extended by 2007, 264:29, XIX extended by 2009, 145:19, 13 extended by 2011, 253:28, 31 for enterprise resource planning.

29. The appropriation made to the community college system in 2011, 253:1, XVI, A for Manchester community college student center.

30. The appropriation made to the community college system in 2011, 253:1, XVI, B for career/tech building.

31. The appropriation made to the community college system in 2009, 145:1, III, A extended by 2011, 253:28, 34 for critical maintenance.

32. The appropriation made to the community college system in 2009, 145:1, III, E extended by 2011, 253:28, 35 for health science and tech building, Nashua.

33. The appropriation made to the department of corrections in 2009, 145:1, IV, A extended by 2011, 253:28, 36 for women's prison and transitional housing site/design.

34. The appropriation made to the department of corrections in 2009, 145:1, IV, B extended by 2011, 253:28, 37 for MSU dorms, CCU, SPU, MCS, MCN bathroom repair.

35. The appropriation made to the department of corrections in 2009, 145:1, IV, D extended by 2011, 253:28, 39 for admin east wing-upgrade electric wiring.

36. The appropriation made to the department of corrections in 2007, 264:1, V, A extended by 2009, 145:19, 23 extended by 2011, 253:28, 43 for electronic security upgrades-men’s prison.

37. The appropriation made to the department of education in 2011, 253:1, IV, A for pre-engineering tech career pathway.

38. The appropriation made to the department of education in 2011, 253:1, IV, B for CTE center renovation-Pinkerton.

39. The appropriation made to the department of education in 2011, 253:1, IV, C for CTE center renovation-Laconia.

40. The appropriation made to the department of education in 2009, 145:1, V, A extended by 2011, 253:28, 46 for pre-engineering technology.

41. The appropriation made to the department of employment security in 2011, 253:1, V, A for Tobey building renovation and garage construction.

42. The appropriation made to the department of environmental services in 2011, 253:1, VI, A for clean water state revolving fund loan program.

43. The appropriation made to the department of environmental services in 2011, 253:1, VI, B for drinking water state revolving fund state match.

44. The appropriation made to the department of environmental services in 2011, 253:1, VI, C for dam repairs and reconstruction.

45. The appropriation made to the department of environmental services in 2011, 253:1, VI, D for Great Bay oil spill protection strategy.

46. The appropriation made to the department of environmental services in 2011, 253:1, VI, E for WRBP infrastructure capital improvements.

47. The appropriation made to the department of environmental services in 2011, 253:1, VI, F for Suncook river infrastructure protection project.

48. The appropriation made to the department of environmental services in 2009, 145:1, VI, A extended by 2011, 253:28, 50 for WRBP wastewater treatment plant improvements.

49. The appropriation made to the department of environmental services in 2009, 145:1, VI, B extended by 2011, 253:28, 51 for drinking water state revolving fund matching funds.

50. The appropriation made to the department of environmental services in 2007, 264:1, VII, A extended by 2009, 145:19, 38 extended by 2011, 253:28, 58 for drinking water state revolving fund matching funds.

51. The appropriation made to the department of environmental services in 2007, 264:1, VII, B extended by 2009, 145:19, 39 extended by 2011, 253:28, 59 for wastewater state revolving fund matching funds.

52. The appropriation made to the department of environmental services in 2007, 264:1, VII, F, as extended by 2009, 145:19, 43, and 2011, 253:28, 61 for dam repairs, removal and reconstruction.

53. The appropriation made to the department of environmental services in 2003, 240:1, V, A extended by 2005, 259:25, XXVIII extended by 2007, 264:29, XXXV extended by 2009, 145:19, 31 extended by 2011, 253:28, 53 for hazardous waste superfund match.

54. The appropriation made to the department of fish and game in 2011, 253:1, XVII, A for Jones pond dam repair and reconstruction.

55. The appropriation made to the department of fish and game in 2009, 145:3, III extended by 2011, 253:28, 63 for point of service registration.

56. The appropriation made to the department of fish and game in 2005, 259:3, II extended by 2007, 264:29, XLVI extended by 2009, 145:19, 45 extended by 2011, 253:28, 64 for hatchery system modernization.

57. The appropriation made to the department of health and human services in 2011, 253:1, VII, A for fire protection sprinklers.

58. The appropriation made to the department of health and human services in 2011, 253:1, VII, B for admin building fire safety/ADA compliance.

59. The appropriation made to the department of health and human services in 2011, 253:1, VII, D for APS repair/renovations-roof, windows and curtain wall.

60. The appropriation made to the department of health and human services in 2011, 253:1, VII, E for boiler house building-new roof.

61. The appropriation made to the department of health and human services in 2011, 253:1, VII, G for incremental renewal of New Heights.

62. The appropriation made to the department of health and human services in 2011, 253:1, VII, H for electronic health records.

63. The appropriation made to the department of health and human services in 2011, 253:1, VII, I for regional assessments database II.

64. The appropriation made to the department of health and human services in 2011, 253:1, VII, J for video conferencing-administrative appeals unit.

65. The appropriation made to the department of health and human services in 2011, 253:1, VII, L for replatform option application.

66. The appropriation made to the department of health and human services in 2011, 253:1, VII, M for admin building handicap access and elevator.

67. The appropriation made to the department of health and human services in 2011, 253:1, VII, N for DPHS radiochemistry lab improvements.

68. The appropriation made to the department of health and human services in 2011, 253:1, VII, P for Howard rec. building renovations, roof and brickwork.

69. The appropriation made to the department of health and human services in 2011, 253:1, VII, Q for ACCESS front door release II.

70. The appropriation made to the department of health and human services in 2009, 145:1, VII, B extended by 2011, 253:28, 65 for incremental renewal of HEIGHTS phase II.

71. The appropriation made to the department of health and human services in 2009, 145:17, IV, C extended by 2011, 253:28, 67 for strategic plan for legacy systems, 50-50 federal match.

72. The appropriation made to the department of health and human services in 2007, 264:1, IX, C, as amended by 2009, 145:18, as extended by 2009, 145:19, 50, and 2011, 253:28, 69 for Glencliff-Brown building patient room floor abatement, tunnel repair, admin. building roof replacement.

73. The appropriation made to the department of information technology in 2011, 253:1, VIII, B for network operations infrastructure upgrade and VOIP.

74. The appropriation made to the department of information technology in 2011, 253:1, VIII, C for business one stop center.

75. The appropriation made to the judicial branch in 2011, 253:1, IX, A for prisoner video conference.

76. The appropriation made to the judicial branch in 2011, 253:1, IX, B for call center.

77. The appropriation made to the judicial branch in 2011, 253:1, IX, C for e-court initiative.

78. The appropriation made to the liquor commission in 2011, 253:1, X, A for Hooksett north and south store additions.

79. The appropriation made to the liquor commission in 2011, 253:1, X, C for Chesterfield-new store.

80. The appropriation made to the Pease development authority in 2007, 264:1, XII, B as amended by 2008, 5:1 extended by 2009, 145:19, 54 extended by 2011, 253:28, 74 for Rye harbor commercial fish pier.

81. The appropriation made to the department of resources and economic development in 2011, 253:1, XII, A for fire tower maintenance.

82. The appropriation made to the department of resources and economic development in 2011, 253:1, XII, B for state park repairs.

83. The appropriation made to the department of resources and economic development in 2011, 253:1, XII, C for Mt. Washington-Adams building concrete repair.

84. The appropriation made to the department of resources and economic development in 2011, 253:1, XII, F for Cannon Mtn upgrades-snowmaking.

85. The appropriation made to the department of resources and economic development in 2009, 145:1, X, C extended by 2011, 253:28, 77 for Mittersill expansion.

86. The appropriation made to the department of resources and economic development in 2009, 145:1, X, B, as extended by 2011, 253:28, 76 for Mount Washington tip top house repairs.

87. The appropriation made to the department of revenue administration in 2009, 145:1, XI, A extended by 2011, 253:28, 82 for tax system 2010.

88. The appropriation made to the department of safety in 2011, 253:1, XIII, A for e-911 next generation.

89. The appropriation made to the department of safety in 2011, 253:1, XIII, B for Suncook river property acquisition and hazard mitigation.

90. The appropriation made to the department of safety in 2011, 253:2, II, A, as amended by section 16 of this act for Hayes building standby generator replacement, computer room A/C upgrade, and DMV HQ generator.

91. The appropriation made to the department of safety in 2009, 145:2, I, A extended by 2011, 253:28, 83 for DMV VISION project continuation.

92. The appropriation made to the department of safety in 2007, 264:2, I, D extended by 2009, 145:19, 63 extended by 2011, 253:28, 87 for OIT projects for DMV.

93. The appropriation made to the department of transportation in 2011, 253:1, XIV, A for 2.5 percent match for FAA projects.

94. The appropriation made to the department of transportation in 2011, 253:1, XIV, B for bus replacement-transit match.

95. The appropriation made to the department of transportation in 2011, 253:2, III, A for underground fuel tank replacement.

96. The appropriation made to the department of transportation in 2011, 253:2, III, B for statewide radio communication replacement.

97. The appropriation made to the department of transportation in 2011, 253:2, III, C for statewide salt sheds.

98. The appropriation made to the department of transportation in 2011, 253:2, III, D for new patrol shed and salt storage-Salem.

99. The appropriation made to the department of transportation in 2011, 253:2, III, E for data center TMC equipment room upgrade.

100. The appropriation made to the department of transportation in 2009, 145:1, XII, A extended by 2011, 253:28, 88 for FAA projects.

101. The appropriation made to the department of transportation in 2009, 145:1, XII, B extended by 2011, 253:28, 89 for public transit bus matching funds.

102. The appropriation made to the department of transportation in 2009, 145:1, XII, C extended by 2011, 253:28, 90 for airport navigation equipment.

103. The appropriation made to the department of transportation in 2009, 145:1, XII, E extended by 2011, 253:28, 92 for state owned rail bridge repair.

104. The appropriation made to the department of transportation in 2009, 145:2, II, C extended by 2011, 253:28, 94 for replacement of automated fueling system-phase 2.

105. The appropriation made to the department of transportation in 2007, 264:1, XIV, A extended by 2009, 145:19, 65 extended by 2011, 253:28, 99 for 5-10 percent match for FAA projects.

106. The appropriation made to the department of transportation in 2007, 264:1, XIV, C extended by 2009, 145:19, 67 amended by 2011, 253:16 extended by 2011, 253:28, 100 for rail match.

107. The appropriation made to the department of transportation in 2007, 264:2, II, E extended by 2009, 145:19, 74 extended by 2011, 253:28, 102 for fuel center computer system.

108. The appropriation made to the department of transportation in 2007, 264:1, XIV, B extended by 2009, 145:19, 66 extended by 2011, 253:28, 103 for public transit bus replacement.

109. The appropriation made to the department of transportation in 2005, 259:1, XIII, F amended by 2007, 264:20, extended by 2007, 264:29 extended by 2009, 145:19, 81 extended by 2011, 253:28, 104 for railroad acquisition right of first refusal rail match.

110. The appropriation made to the department of transportation in 1999, 226:1, XIII, C, extended by 2001, 202:28, XXXIII extended by 2003, 240:34, LXXVI extended by 2005, 259:25, LVI extended by 2007, 264:29 LXXIV extended by 2009, 145:19, 64 extended by 2011, 253:28, 98 for acquisition for railroad and airport properties.

111. The appropriation made to the New Hampshire veterans' home in 2011, 253:1, XV, A for electronic medical records.

27 Effective Date.

I. Section 26 of this act shall take effect June 30, 2013.

II. The remainder of this act shall take effect July 1, 2013.

LBAO

13-1020

Amended 04/05/13

HB 25 FISCAL NOTE

AN ACT making appropriations for capital improvements.

FISCAL IMPACT:

      The Treasury Department states this bill, as amended by the House (Amendment #2013-1150h), will increase state general fund expenditures by $1,552,517 in FY 2014, $8,290,443 in FY 2015, $13,289,549 in FY 2016, $12,916,945 in FY 2017. This bill will have no impact on state, county and local revenue, or county and local expenditures. This bill increases bonded indebtedness supported by the general fund by $124,201,396.

METHODOLOGY:

    The State Treasury has indicated that the amount of total outstanding direct general obligation bonded indebtedness on behalf of and incurred by the state as of June 30, 2012 is $960 million (not including bond anticipation notes outstanding).  The amount of net general obligation bonded indebtedness (general improvement plus University System of New Hampshire bonds), as of June 30, 2012 is $685.3 million.  The estimated amount of net general obligation bonds authorized, but unissued, as of November 30, 2012 is $132 million.

    The Treasury Department has assumed that one-half the proposed bond authorization will be issued in FY 2014 and one-half in FY 2015.  Current interest bond rates are fixed at 5% and amortized over 20 years (60% of the principal paid in the first ten years, 40% paid in the second 10 years).  An estimated debt retirement schedule for all outstanding direct general obligation bonded indebtedness, including the proposed authorization contained in this bill through FY 2017, is displayed below (in thousands):

                    Fiscal Existing Additional Total Year Debt Obligation Debt Obligation Debt Obligation 2014 $82,319 $1,553 $83,872

                    2015 $78,366 $8,290 $86,656

                    2016 $76,646 $13,290 $89,936

                    2017 $75,844 $12,917 $88,761

    The bill also authorizes $13,277,500 of highway bonds, and $38,951,852 of other bonds, and the receipt of $50,802,565 in federal funds.