Amend 2018, 340:2, I of section 1 of the bill by replacing it with the following:
I. Further Suspension of Operation of Cap. The public utilities commission shall amend its Order No. 25,213 and its Order No. 26,198 and Order No. 26,333 issued in Docket DE 10-195 to extend the suspension of the operation of the cap on the cumulative reduction factor as set forth on page 97 of Order No. 25,213 for an additional period of 2 years from the date the operation of the cap would have otherwise taken effect under Order No. 25,213 and Order No. 26,198 and Order No. 26,333.