113:1 Sewage Disposal Systems; Approval to Increase Load on a Sewage Disposal System. Amend the introductory paragraph of RSA 485-A:38, I to read as follows:

I. Prior to expanding any structure or occupying any existing structure on a full-time basis , which would increase the load on a sewage disposal system, the owner of such structure shall submit an application for approval of the sewage disposal system to the department. Application for approval shall include one of the following:

113:2 Approval to Increase Load on a Sewage Disposal System. Amend RSA 485-A:38, II-a(a)(1)(B)-(C) to read as follows:

(B) The lot is 5 acres or more in size ; or

(C) The lot is served by an off lot effluent disposal area .

113:3 Effective Date. This act shall take effect 60 days after its passage.

Approved: July 03, 2024

Effective Date: September 01, 2024

Changed Version

Text to be added highlighted in green.

113:1 Sewage Disposal Systems; Approval to Increase Load on a Sewage Disposal System. Amend the introductory paragraph of RSA 485-A:38, I to read as follows:

I. Prior to expanding any structure or any change in use , which would increase the load on a sewage disposal system, the owner of such structure shall submit an application for approval of the sewage disposal system to the department. Application for approval shall include one of the following:

113:2 Approval to Increase Load on a Sewage Disposal System. Amend RSA 485-A:38, II-a(a)(1)(B)-(C) to read as follows:

(B) The lot is 5 acres or more in size and is served by a sewage disposal system that received construction and operational approval from the department ; or

(C) The lot is served by a sewage disposal system with an off lot effluent disposal area that received construction and operational approval from the department .

113:3 Effective Date. This act shall take effect 60 days after its passage.

Approved: July 03, 2024

Effective Date: September 01, 2024